Project Timeline

Jan. 2007 Certification request for pipeline filed in IRP with PSC
March 2007 Pipeline route announced and easement acquisition began
Sept. 2007 Public Service Commission approved combined-cycle units and pipeline
Oct. 2008 - April 2009 Final surveying for pipeline construction
Nov. 2008 - April 2009 Vegetation clearing for pipeline within transmission right-of-way
March 2009 Pipeline construction begins
June 2010 Pipeline completed and becomes operational