Project Timeline
| Jan. 2007 | Certification request for pipeline filed in IRP with PSC |
| March 2007 | Pipeline route announced and easement acquisition began |
| Sept. 2007 | Public Service Commission approved combined-cycle units and pipeline |
| Oct. 2008 - April 2009 | Final surveying for pipeline construction |
| Nov. 2008 - April 2009 | Vegetation clearing for pipeline within transmission right-of-way |
| March 2009 | Pipeline construction begins |
| June 2010 | Pipeline completed and becomes operational |