The Relicensing Process
Integrated Licensing Process (ILP)
The ILP was established by FERC regulations (18 C.F.R. Part 5) on July 23, 2003. The ILP provides for increased public participation and consultation prior to filing the relicensing application. Learn more about the ILP, including a process timetable at
www.ferc.gov/industries/hydropower/gen-info/licensing/ilp.asp.
| 2003 | Relicensing background data collection begins |
| Jan-2004 | Georgia Power files Preliminary Application Document (PAD) |
| Apr-2004 | FERC Scoping Meetings & Site Visit |
| Jun-2004 | Georgia Power files Study Plan with FERC |
| Jul-2004 | Study Plan Meetings |
| 2004 - 2005 | Georgia Power conducts studies in resource areas |
| Nov-2005 | Georgia Power files Study Plan Progress Report |
| Apr-2006 | Georgia Power files Final Study Reports |
| Study Report Meetings with Stakeholders |
| Oct-2006 | Georgia Power files licensing proposal |
| Feb-2007 | Georgia Power files License Application |