Schedule

Schedule Information

Key Dates (Section 6)
Begin Clearing/Grading November 2017
Begin Line Construction of Section 6 (Estimated) September 2018
End Clearing/Grading Section 6 (Estimated) June 2019
End ROW Restoration Section 6 (Estimated) July 2019