Skip to main content.
powerlines over a bluesky

Conyers - Klondike

230 kV Transmission Line Project

As part of our investments in our statewide transmission system, we are constructing a new 8.5-mile transmission line connecting the Conyers Substation to the Klondike Substation. These investments are necessary to support Georgia’s growing energy needs and ensure that we can continue to reliably serve our customers with energy for decades to come.


About the Project

The Conyers – Klondike 230 kV project consists of a new 8.5-mile transmission line that will run between the Conyers Substation in Rockdale County and the Klondike Substation in Dekalb County. In some locations, the Conyers–Klondike 230 kV transmission line will follow the existing Conyers - Klondike 230 kV transmission corridor. In other areas, a new corridor will be created where required by the project design.

This project is part of our ongoing commitment to strengthen and expand the electric grid. This critical infrastructure is designed to enhance system reliability, support Georgia’s evolving energy needs, and ensure safe, resilient service for decades to come.

Project Timeline

  • Q2 - Q3 2025: Survey notifications to landowners
  • Q2 - Q3 2026: Community meetings
  • Q3 - Q4 2026: Easement acquisition
  • Q4 2026: Line clearing and grading begins
  • Q1 2027: Line construction begins
  • Q1 2028: Project completion

Note: This schedule is tentative and subject to change.

MAP NOT BASED ON FIELD SURVEY DATA

Structure and Line Locations based on Pre-Engineering data and subject to change

  •   Substation
  •   Proposed transmission line

Please note:
If your property is directly affected, you will be contacted personally by a Georgia Power representative or authorized third party.

If you're located near the project, general updates will be shared to keep you informed of key milestones and progress.

Project Benefits

icon

Strengthens the electric grid to provide reliable power today and into the future.

icon

Supports growing energy needs across Georgia’s communities.

icon

Improves system performance by adding resilient transmission pathways and increasing operational efficiency.


What to Expect

As the project progresses, you may experience different impacts depending on your location in relation to the project. Below are some examples of what you may encounter:

  • Vegetation Removal
    Crews will remove trees, brush, and other vegetation along the transmission line route to ensure compliance with safety standards and required clearances. All work will be conducted with careful consideration to minimize environmental and landowner impact.

  • Site Grading
    Equipment will be used to smooth and level the ground, providing stable access for construction activities. This helps ensure safe and efficient work zones for crews.

  • Construction Activities
    Construction work, including drilling, installation of poles and wires, and the use of bucket trucks and cranes, will be occurring in the area in various phases. These activities are essential for building the new transmission line and may result in intermittent lane closures or temporary access roads in some areas.

  • Noise and Traffic
    Expect some construction noise and increased vehicle activity. We will work to minimize disruptions and maintain safe access for residents and local traffic.

  • Restoration
    Once construction is complete, the site and surrounding areas will be cleared of debris, graded, and left in a clean, orderly condition that supports long-term safety and environmental compliance.

Communication

We are committed to keeping residents, business owners, and community members informed throughout Conyers – Klondike 230kV Transmission Line Project. Project updates will be shared on our website as new information becomes available, and you may also receive mailed updates depending on your location.

Please review the Frequently Asked Questions below or contact us directly with any questions or concerns. Your feedback is important, and we encourage you to reach out so we can provide the support and information you need throughout the project.



Have questions about this project?

Below are answers to common questions and what you can expect as work moves forward.

About the Project

What is this project and why is it happening?

Georgia Power is constructing a new 8.5-mile, 230kV transmission line connecting the Conyers Substation in Rockdale County to the Klondike Substation in Dekalb County. In some locations, the Conyers–Klondike 230kV transmission line will follow the existing Conyers - Klondike 230kV transmission corridor. In other areas, a new corridor will be created where required by the project design. This project is part of Georgia Power’s ongoing commitment to strengthen and expand the electric grid. Over the next 10 years, we have proposed building more than 1,000 miles of new transmission lines to improve efficiency and resiliency and serve a growing state. These investments are necessary to support Georgia’s growing energy needs, enhance system reliability, and ensure safe, resilient service for decades to come.

How will this project benefit my community?

This project is part of Georgia Power’s ongoing commitment to strengthen and expand the electric grid. By strengthening the grid for long-term system reliability, preparing for Georgia’s growing energy needs, and supporting the integration of renewable energy sources, this critical infrastructure will help ensure safe, resilient service for your community for decades to come.

How was this route determined?

We have a thorough process for determining transmission line routing and facility placement. We carefully evaluate routes and consider factors such as safety, existing land uses in the area, existing transmission corridors, environmental conditions, engineering practices related to the construction and operation of the lines, and cost impact to customers associated with the construction, operation, and maintenance of the line.

Is this transmission line being built to serve a specific customer or facility?

This project is not being built to serve a specific customer or facility. The Conyers – Klondike 230kV Transmission Line is part of Georgia Power’s broader, long-term investment in strengthening and expanding the electric grid across the state. Over the next 10 years, we have proposed building more than 1,000 miles of new transmission lines to improve efficiency and resiliency and serve a growing state. These projects are essential to support Georgia’s growing energy needs, improve system reliability, and ensure safe, resilient service for decades to come.

Will trees or vegetation be removed?

Vegetation removal is part of the project, including the removal of trees, brush, and other vegetation along the transmission line route to ensure compliance with safety standards and required clearances. All work will be conducted with careful consideration to minimize environmental impact, and restoration will follow construction.

How can I stay updated on the project?

We will share updates, maps, and key milestones on this webpage.

 

Community meetings scheduled during Q2 2026 will provide opportunities to learn more, ask questions, and engage directly with project experts on topics such as land acquisition, environmental considerations, and construction timelines. If you have questions at any time, you can contact the project team directly using this form.

General Questions

What are transmission lines?

Transmission lines transmit high-voltage electricity from the generation source or substation to another substation in the electric grid. Overhead transmission lines carry a three-phase current and can vary in voltage. Learn more.

What is a line route?

A line route refers to the path or corridor that a transmission line follows from its starting point to its endpoint. The route is selected based on various considerations, including safety, existing land uses in the area, existing transmission corridors, environmental conditions, engineering practices related to the construction and operation of the lines, and cost impact to customers associated with the construction, operation, and maintenance of the line.

What is an easement?

An easement is a legal right to use another person's land for a specific purpose, where a fee is paid to the owner of the property in return for the right of easement. This right allows the easement holder to enter and use the land for activities such as utility installation, access, or maintenance. The original owner retains legal title to the land, but the easement holder has the right to use it as specified in the easement agreement.

Are there health risks or safety concerns from living near substations or power lines?

Decades of research show no link between EMF exposure from power lines and disease. EMFs are common in everyday electrical devices, and power lines meet national safety standards.

We are committed to keeping residents, business owners, and all community members informed throughout every stage of the project. Please submit any questions you have here. Your feedback is important, and we encourage you to reach out so we can provide the support and information you need throughout the project.