Solar companies often assist with the application and interconnection process when installing behind-the-meter solar on behalf of Georgia Power customers.
To help aid that process, we've compiled the below resources to to ensure a smooth interconnection process for our mutual customer.
We strongly recommend submitting applications as early as possible – before construction begins – to allow for a thorough review of potential system impacts. Customers should refrain from purchasing any facility equipment or starting construction until Georgia Power has reviewed the application and confirmed how the facility can be integrated with existing Georgia Power equipment and service
For information about installation requirements and best practices, reference the following:
PowerClerk is the primary source for your project status and updates throughout the interconnection process.
A Georgia Power Project Manager will review the application and approve it if no edits are needed.
If edits are required, the project will be returned and any edits or updates are needed will be noted.
Installer will notify Georgia Power via PowerClerk that installation is complete, the system has passed county inspection, and the project is ready for witness testing.
The customer will receive a copy of the interconnection agreement via their email through DocuSign. The agreement will need to be reviewed for accuracy and signed electronically.
A Georgia Power meter reader and Third-Party contractor will visit the location of the solar installation to perform the witness test and reprogram the meter to bi-directional.
Once all steps have been successfully completed, the customer will receive an email from Georgia Power granting permission to turn their system on and begin generating.
RNR Instantaneous Netting program allows customers to be compensated for excess solar production sent to the Georgia Power grid.
Energy Offset program allows customers to maximize the amount of energy they offset with no system size limitations.
Solar systems that meet the requirements to participate as a Qualifying Facility may sell the excess or 100% of the solar generation to Georgia Power. For more information about the Qualifying Facilities program, you can visit our Qualifying Facilities page.
Excess energy generated by a participating customer’s solar panels are credited at the annual Solar Avoided Energy Cost Rate plus an additional 4¢ per kilowatt hour (kWh), summed on a monthly basis and then will be used to reduce the customer’s total monthly bill. To move forward with installation and connection to the grid, customers will need to sign an RNR Instantaneous (RNR) Service and Interconnection Agreement.
System limitation size of less than or equal to 10 kW AC.
This program is currently open for participation as further detailed in the RNR Tariff.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.
This program is ideal for customers who want to install a solar system that helps offset as much of their energy use as possible. It supports systems of any size, giving you the flexibility to design a solution that fits your needs. If your system passes the engineering review without any limitations, you may be able to send any excess energy back to the grid. However, please note that exported energy is not eligible for compensation under this program. In some cases, systems that require non-export controls may also qualify. There are no additional tariffs or bill credits associated with participation. To move forward with installation and connection to the grid, customers will need to sign an Energy Offset Only (EOO) Service and Interconnection Agreement.
Residential projects larger than 10 kW are automatically enrolled in Energy Offset Only.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.
Project Size: ≤ 10 kW AC
Program: RNR or Energy Offset Only
Interconnection Fee: $100
Project Size: > 10 kW AC
Program: Energy Offset Only
Interconnection Fee: $100
The interconnection fee is added as a line item on the customer's bill after the interconnection process is completed.
The impact study will determine if the solar system poses any risks to safety and reliability. At this time, fees are charged to customers only.
Projects less than 250kW AC will not be charged an impact study fee
Projects greater than 250kW AC will be charged an impact study fee that ranges from $1,930 – $5,700.
The impact study cost for customers connected to our Network Underground is $2,400.
For information about installation requirements and best practices, reference the following:
The customer or installer submits basic project information in PowerClerk, including account details, site address, system and installer information, program selection, and an aerial screenshot.
Georgia Power engineers perform an initial, complimentary Feasibility Analysis of initial materials.
Once the results are confirmed, Georgia Power will conduct further technical review to evaluate potential grid impacts and identify any preliminary upgrade needs or constraints.
A Georgia Power Project Coordinator will prepare and issue the Service and Interconnection Agreement for signature. Upon execution and review, the customer may proceed with construction.
After construction is complete, the customer will notify Georgia Power that the facility is ready for witness testing.
We strongly recommend submitting applications as early as possible – before construction begins – to allow for a thorough review of potential system impacts and potential costs.
Witness Tests are scheduled and conducted by a Third-Party contractor, who checks the system to ensure that the facility can be safely integrated with existing Georgia Power equipment and service.
After an Interconnection Agreement has been executed and the Witness Test has been passed, Georgia Power will issue official Permission to Operate documentation, and the system can officially be turned on and generating.
We have several programs designed to help customers reach their renewable energy goals.
RNR Instantaneous Netting program allows customers to be compensated for excess solar production sent to the Georgia Power grid.
Energy Offset Only program allows customers to maximize the amount of energy they offset with no system size limitations.
Solar systems that meet the requirements to participate as a Qualifying Facility may sell the excess or 100% of the solar generation to Georgia Power. For more information about the Qualifying Facilities program, you can visit our Qualifying Facilities page.
Excess energy generated by a participating customer’s solar panels are credited at the annual Solar Avoided Energy Cost Rate plus an additional 4¢ per kilowatt hour (kWh), summed on a monthly basis and then will be used to reduce the customer’s total monthly bill. To move forward with installation and connection to the grid, customers will need to sign an RNR Instantaneous (RNR) Service and Interconnection Agreement.
This program is currently open for participation as further detailed in the RNR Tariff.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.
This program is designed for customers who wish to maximize the size of their solar installation to offset their energy usage. This program is available for systems of any size, including those greater than 250 kW. If no limitations are identified during the engineering review, the facility may export excess generation to the grid; however, customers will not receive compensation for exported energy. Systems requiring non-export controls may also fall under the EOO designation. Participation in this program does not result in additional tariffs or bill credits. Customers must sign an Interconnection Agreement specific to EOO to proceed with installation and interconnection. To move forward with installation and connection to the grid, customers will need to sign an Energy Offset Only (EOO) Service and Interconnection Agreement.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.
Project Size: ≤ 250 kW AC
Program: RNR or Energy Offset Only
Interconnection Fee Cost: $200
Project Size: ≥ 250 kW + < 1MW and < 250 kW+ Three Phase
Program: Energy Offset Only
Witness Test Fee Cost: $3,900 (weekday)—$4,400 (weekend)
Project Size: ≥ 1MW
Program: Energy Offset Only
Witness Test Fee Cost: $3,200 (weekday)—$4,700 (weekend)
*Projects >250 will have an Interconnection and Witness Test fee
For projects less than or equal to 250kW AC, the interconnection fee is added as a line item on the customer's bill after the interconnection process is completed.
Any projects that are greater than 250kW AC will also be charged a witness test fee billed to the customer through a Non-Electric Service Business (NESB). At this time, fees are charged to customers only.
For applicants without existing accounts, the fees will be invoiced
The impact study will determine if the solar system poses any risks to safety and reliability. The fee is charged to the customer through a Non-Electric Service Business (NESB). At this time, fees are charged to customers only.
Projects greater than 250kW AC will be charged an impact study fee that ranges from $1,930 – $5,700.
The impact study cost for customers connected to our Network Underground is $2,400.
To participate in either program, you must fill out an application using PowerClerk, our interconnection for application tool.
To get started with your application, please register to create an account.
Applications may be filled out by the installer or the customer and both parties may be granted access to view the project status.
All applications will require the Georgia Power customer’s approval and the customer will be required to sign an interconnection agreement.
Information may be entered into the application as it is available, and the application will be automatically saved as changes and updates are made.
A completed application will include the following:
Distributed energy generators should reference the following documents to ensure their facilities comply with the Company’s safety, reliability, operating and interconnection requirements:
Witness Tests are conducted on all solar generators on Georgia Power’s distribution or transmission system to ensure generators meet the Company’s safety, reliability, and interconnection requirements.
For projects less than 250kW AC, the Witness Test is scheduled by a third-party contractor. The contractor will reach out to the person listed as the Witness Test contact provided by the installer with an estimated date and time of arrival to perform the Witness Test.
For projects larger than 250kW AC, the Georgia Power project manager will contact the customer and contractor to schedule the Witness Test.
For rescheduling a witness test, please ensure the appropriate forms are completed in PowerClerk. We will review the request and reach out if any additional information is needed.
If a project does not pass the witness test, the installer and customer will be notified of the reason for the failure. and any required corrective actions. Common issues may include equipment settings that do not operate as expected, discrepancies between the installed equipment and the approved one-line diagram, an inverter (or multiple) being inoperable, or other safety and operational requirements identified during testing.
Once the necessary corrections have been made, the project will need to be rescheduled in PowerClerk for additional review or witness testing. Final Permission to Operate (PTO) cannot be granted until all identified issues have been resolved and the project successfully meets Georgia Power's interconnection requirements.
Once your project has successfully completed the final steps, it will be officially approved and ready to operate. After passing the required testing, updating your meter for two-way energy flow, and finalizing all documentation, your system will be marked as “Online.” At that point, you and your installer will receive an official Permission to Operate (PTO) letter via email, confirming that your system is approved and ready to generate energy.
If there are any changes in ownership, system modifications, or additions after the project receives PTO, the contractor or customer must revise the original application in PowerClerk to reflect the changes. A new or amended agreement will be generated for the customer’s signature. Systems must remain off until Georgia Power has given final PTO.
Each project requires two site visits prior to Permission to Operate:
The third-party contractor is responsible for scheduling the witness test and will contact the installer-provided witness test contact to coordinate an estimated date and time of arrival.
Do not submit a new application.
Instead, request edits to the existing application in PowerClerk so the system accurately reflects the installed equipment.
Projects may be returned for edits during review if updates are needed, and once corrected, they can proceed through the standard interconnection process.
If a new installer is taking over the project, coordination with Georgia Power is required to update their application.
A New Contractor Information Form will be provided to the customer for completion before the installer is granted access to their application and submit edits on the customer's behalf. Please provide the customer with an email address that is registered to PowerClerk and we will make sure the project is successfully transferred to your team.
For information about installation requirements and best practices, reference the following:
PowerClerk is the primary source for your project status and updates throughout the interconnection process.
A Georgia Power Project Manager will review the application and approve it if no edits are needed.
If edits are required, the project will be returned and any edits or updates are needed will be noted.
Don't forget to update PowerClerk after installation is complete, passed inspection, and the project is ready for witness testing.
A Georgia Power meterman will visit the location of the solar installation to perform the witness test and reprogram the meter to bi-directional.
Once all steps have been successfully completed, the customer will receive an email from Georgia Power granting permission to turn their system on and begin generating.
We have several programs designed to to help customers, who plan to install solar, offset their usage.
RNR Instantaneous Netting program allows customers to be compensated for excess solar production sent to the Georgia Power grid.
Energy Offset program allows customers to maximize the amount of energy they offset with no system size limitations.
Solar systems that meet the requirements to participate as a Qualifying Facility may sell the excess or 100% of the solar generation to Georgia Power. For more information about the Qualifying Facilities program, you can visit our Qualifying Facilities page.
Excess energy generated by a participating customer’s solar panels are credited at the annual Solar Avoided Energy Cost Rate plus an additional 4¢ per kilowatt hour (kWh), summed on a monthly basis and then will be used to reduce the customer’s total monthly bill.
This program is currently open for participation as further detailed in the RNR Tariff.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.
Project Size: ≤ 250 kW AC
Program: RNR or Energy Offset Only
Interconnection Fee Cost: $200
Project Size: > 250 kW AC
Program: Energy Offset Only
Witness Test Fee Cost: $3,900 (weekday)—$4,400 (weekend)
*Projects >250 will have an Interconnection and Witness Test fee
For projects less than or equal to 250kW AC, the interconnection fee is added as a line item on the customer's bill after the interconnection process is completed.
Any projects that are greater than 250kW AC will also be charged a witness test fee billed to the customer through a Non-Electric Service Business (NESB). At this time, fees are charged to customers only.
The impact study will determine if the solar system poses any risks to safety and reliability. The fee is charged to the customer through a Non-Electric Service Business (NESB). At this time, fees are charged to customers only.
Projects greater than 250kW AC will be charged an impact study fee that ranges from $1,930 – $5,700.
The impact study cost for customers connected to our Network Underground is $2,400.
Designed for commercial customers who would like to maximize the size of the solar installation, in order to offset their energy usage.
Systems are not designed to push energy back onto the grid, and will not be compensated for any excess energy that is generated.
Any customer that has solar installed behind their meter who has not elected to participate in one of our other programs, will be automatically enrolled in this program.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.
For information about installation requirements and best practices, reference the following:
PowerClerk is the primary source for your project status and updates throughout the interconnection process.
A Georgia Power Project Manager will review the application and approve it if no edits are needed.
If edits are required, the project will be returned and any edits or updates are needed will be noted.
Don't forget to update PowerClerk after installation is complete, passed inspection, and the project is ready for witness testing.
A Georgia Power meterman will visit the location of the solar installation to perform the witness test and reprogram the meter to bi-directional.
Once all steps have been successfully completed, the customer will receive an email from Georgia Power granting permission to turn their system on and begin generating.
We have several programs designed to to help customers, who plan to install solar, offset their usage.
RNR Instantaneous Netting program allows customers to be compensated for excess solar production sent to the Georgia Power grid.
Energy Offset program allows customers to maximize the amount of energy they offset with no system size limitations.
Solar systems that meet the requirements to participate as a Qualifying Facility may sell the excess or 100% of the solar generation to Georgia Power. For more information about the Qualifying Facilities program, you can visit our Qualifying Facilities page.
Excess energy generated by a participating customer’s solar panels are credited at the annual Solar Avoided Energy Cost Rate plus an additional 4¢ per kilowatt hour (kWh), summed on a monthly basis and then will be used to reduce the customer’s total monthly bill.
This program is currently open for participation as further detailed in the RNR Tariff.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.
Project Size: ≤ 250 kW AC
Program: RNR or Energy Offset Only
Interconnection Fee Cost: $200
Project Size: > 250 kW AC
Program: Energy Offset Only
Witness Test Fee Cost: $3,900 (weekday)—$4,400 (weekend)
*Projects >250 will have an Interconnection and Witness Test fee
For projects less than or equal to 250kW AC, the interconnection fee is added as a line item on the customer's bill after the interconnection process is completed.
Any projects that are greater than 250kW AC will also be charged a witness test fee billed to the customer through a Non-Electric Service Business (NESB). At this time, fees are charged to customers only.
The impact study will determine if the solar system poses any risks to safety and reliability. The fee is charged to the customer through a Non-Electric Service Business (NESB). At this time, fees are charged to customers only.
Projects greater than 250kW AC will be charged an impact study fee that ranges from $1,930 – $5,700.
The impact study cost for customers connected to our Network Underground is $2,400.
Designed for commercial customers who would like to maximize the size of the solar installation, in order to offset their energy usage.
Systems are not designed to push energy back onto the grid, and will not be compensated for any excess energy that is generated.
Any customer that has solar installed behind their meter who has not elected to participate in one of our other programs, will be automatically enrolled in this program.
Customers are required to register their systems and ensure they meet the Interconnection Requirements.
Register and apply for this program using PowerClerk.