The project is expected to include a new 500/230 kV Effingham County Substation, new 500 kV transmission infrastructure, and associated facilities. The project is being planned to provide the transmission infrastructure needed to serve a large-load customer while also strengthening the local electric grid in a rapidly growing area. These improvements will add capacity, enhance reliability for homes and businesses, and help support continued growth and evolving energy needs.
Although some project elements are designed to meet specific customer requirements, the improvements are also expected to strengthen the transmission network and support future growth. As planning progresses, project details will be refined based on engineering, environmental, and routing studies.
As the project progresses, you may experience different impacts depending on your location in relation to the project. Below are some examples of what you may encounter.
Project timeline is tentative and as planning progresses schedule may change.
| Summer 2026 | Notification to elected officials |
| Summer 2026 | Substation survey notifications to property owners |
| Fall 2026 | Substation land acquisition activities begin |
| Spring 2027 | Substation clearing and grading begins |
| Fall 2027 | Substation construction activities begin |
A project map is not available at this stage of the planning process. As the project advances and additional details are finalized, maps and other project information will be shared on this webpage.
See how we're investing in our communities, protecting Georgians from rising energy costs, and building a reliable energy grid.
As Georgia grows, our pledge reaffirms our commitment to serving and protecting the interests, the communities, and the priorities of our 2.8 million customers—making sure new large-energy users, like data centers, are paying for the infrastructure built to serve them. Learn more about how we're dedicated to keeping energy reliable and affordable while preparing for growth in the state we all call home.
We are committed to empowering education and strengthening our communities through workforce development. Through our support of the RISE Educator Externship Program, we helped provide 20 educators with firsthand experience inside leading manufacturing and logistics companies across Southeast Georgia. By connecting teachers to real-world career opportunities and industry needs, we are helping them bring valuable insights back to the classroom and better prepare students for success in the workforce.
As Georgia grows, customers want to know how it affects their everyday lives. By putting customers at the center, we’re working to ensure growth works for everyone.
We’re investing in generation, smart grid infrastructure, and advanced technologies to deliver reliable energy to 2.7 million customers—every day, in every season.
Throughout this project, you may receive updates via email, letter, postcard or door hanger.
Below are answers to common questions and what you can expect as work moves forward.
The project is expected to include a new 500/230 kV Effingham County Substation, new 500 kV transmission infrastructure, and associated facilities to support the electrical needs of a large-load customer while also strengthening the local transmission system. The project is necessary to provide reliable electric service in an area experiencing continued growth, while ensuring Georgia Power’s transmission network can safely and effectively serve current and future demand. The improvements also enhance overall grid reliability and support long‑term infrastructure needs for the region. Learn more about Transmission Projects
The project will strengthen the local electric grid by adding capacity and improving reliability in Effingham and surrounding counties. The project supports the energy needs of a large-load customer that requires new transmission infrastructure, while also enhancing the system that serves homes, businesses, and critical facilities and increasing flexibility to support future growth and evolving energy needs across the region.
Yes, this project is being developed to serve the electric needs of a large‑load customer that requires new transmission infrastructure. The improvements also enhance the overall system, providing broader reliability benefits for the surrounding area. Learn more about data centers & Georgia Power
We have a thorough process for determining transmission line routing and facility placement. We carefully evaluate routes and consider factors such as safety, existing land uses in the area, existing corridors, environmental conditions, and engineering practices related to the construction and operation of the lines. Learn how Georgia Power selects project locations and routes
Energy infrastructure like transmission lines and substations helps ensure electricity remains reliable and affordable for the communities we serve. As Georgia continues to grow, we must responsibly expand and strengthen the grid to meet increasing demand. Learn more about the land acquisition process.
Transmission lines transmit high-voltage electricity from the generation source or substation to another substation in the electric grid. Overhead transmission lines carry a three-phase current and can vary in voltage. Learn more.
A line route refers to the path or corridor that a transmission line follows from its starting point to its endpoint. The route is selected based on various considerations, including safety, existing land uses in the area, existing transmission corridors, environmental conditions, engineering practices related to the construction and operation of the lines.
The Integrated Resource Plan (IRP) guides investments in generation and transmission to meet forecasted demand, ensuring reliable service for all customers. More about the IRP and our long-term energy planning process managed by the Georgia PSC
An easement is a legal right to use another person's land for a specific purpose, where a payment is paid to the owner of the property in return for the right of easement. This right allows the easement holder to enter and use the land for activities such as utility installation, access, or maintenance. The original owner retains legal title to the land, but the easement holder has the right to use it as specified in the easement agreement.
Decades of research show no link between EMF exposure from power lines and disease. EMFs are common in everyday electrical devices, and power lines meet national safety standards. Read our Electric and Magnetic Fields (EMF) Information Guide (PDF) for an overview of the science and research about EMFs.
We are committed to keeping residents, business owners, and all community members informed throughout every stage of the project. Please submit any questions you have here. Your feedback is important, and we encourage you to reach out so we can provide the support and information you need throughout the project.